**Serbian Government Keeps Train Station Reconstruction Details Secret**

The Serbian government has released many documents about the reconstruction of the train station. However, important financial details remain unknown.

Transparency says that the government published key contract document in June 2021, but not the price table. This table should show how much money was committed to pay certain sections of the railway and works at different stations.

**Lack of Information**

The Serbian Government, , Transport, and Infrastructure, and did not release information about why they thought the price paid for some work was acceptable in and 2021. They agreed a contract worth $1 billion, but only a few million euros were mentioned by government .

**Unclear Process**

The process of selecting subcontractors is unclear. According to the contract, the should have published a public call for tenders. However, no information about how they selected subcontractors is available.

**Transparency Serbia’s Call**

Transparency Serbia calls on the Serbian Government to publish all contracts related to projects implemented without tender. They also want citizens to be informed about how the government determined that the price requested by pre-selected contractors was realistic.